Who has the final decision on whether to release the latest increment?

Prepare for the Professional Scrum Product Owner I (PSPO I) Exam with our interactive quiz. Practice with comprehensive flashcards and multiple choice questions, each crafted to provide hints and thorough explanations. Master the exam with ease and boost your Scrum expertise!

The final decision on whether to release the latest increment rests with the Product Owner. This is because the Product Owner holds the primary responsibility for maximizing the value of the product and ensuring that the increment aligns with stakeholder needs and expectations. They are tasked with understanding customer requirements, prioritizing the backlog, and ultimately deciding when a product increment is ready for release based on its completeness and readiness to deliver value.

The role of the Product Owner involves not only overseeing what features get built but also assessing the overall quality and readiness of the increment for release. This decision is typically made after considering feedback from stakeholders, including input from the Development Team regarding technical readiness, but the ultimate authority lies with the Product Owner as they are responsible for the product's success in the market.

The other roles, while essential in the Scrum framework, do not have the authority to make the release decision. The Development Team contributes to the increment's creation and assesses its readiness, but they do not decide when it goes to market. The Scrum Master acts as a facilitator and coach, supporting the team and helping remove impediments, but does not have a say in release decisions. The Project Manager, in traditional project management frameworks, might exert influence or control over project outputs, but in Scrum, the

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy