Which element should NOT be included in a Sprint Goal?

Prepare for the Professional Scrum Product Owner I (PSPO I) Exam with our interactive quiz. Practice with comprehensive flashcards and multiple choice questions, each crafted to provide hints and thorough explanations. Master the exam with ease and boost your Scrum expertise!

The inclusion of specific team member tasks in a Sprint Goal is not appropriate because the Sprint Goal is intended to articulate a single, overarching objective that the Scrum Team aims to achieve during the Sprint. It serves as a guiding focus for the team, helping to coordinate efforts and make decisions about what work to prioritize without getting bogged down in the specifics of individual responsibilities.

Specific tasks are usually defined within the Sprint Backlog during Sprint Planning and can vary based on the team's dynamics and the work at hand. By focusing on specific tasks, the team might lose sight of the broader goal and could create confusion about the overall purpose of the Sprint. Instead, the Sprint Goal should be about the outcome and the value to be delivered, which allows the team the flexibility to determine the best way to achieve that goal, adapting their tasks as needed throughout the Sprint.

In contrast, including a description of user stories, a precise definition of "Done," and the expected outcome for the Sprint are all elements that can enrich the understanding of what is to be accomplished and contribute to a successful Sprint.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy