What two activities will a Product Owner likely engage in during a Sprint?

Prepare for the Professional Scrum Product Owner I (PSPO I) Exam with our interactive quiz. Practice with comprehensive flashcards and multiple choice questions, each crafted to provide hints and thorough explanations. Master the exam with ease and boost your Scrum expertise!

The selection of activities a Product Owner engages in during a Sprint is critical to ensuring effective collaboration and product delivery. The correct choice highlights two core responsibilities of a Product Owner during a Sprint: answering questions from the Development Team about items in the current Sprint and prioritizing the Product Backlog.

Engaging with the Development Team by answering questions is essential because it ensures clarity and transparency regarding the items being worked on. As the Product Owner is responsible for the Product Backlog, being available to clarify requirements and provide context helps the Development Team make informed decisions while developing the product. This interaction fosters a collaborative environment and helps address any potential roadblocks or misunderstandings that may arise during the Sprint.

Additionally, prioritizing the Product Backlog remains a crucial role during the Sprint. While the Sprint Backlog is typically not altered once the Sprint begins, the Product Owner ensures that the subsequent items in the Product Backlog are well-defined and prioritized for upcoming Sprints. This forward-thinking approach ensures that the Development Team has a clear focus for future work, aligning with the overall product vision and stakeholder needs.

In contrast, the other choices highlight activities that either fall outside the primary responsibilities of a Product Owner or may not align with the Scrum framework's principles. For example, assigning