What occurs if the Development Team cannot complete its work by the end of the Sprint?

Prepare for the Professional Scrum Product Owner I (PSPO I) Exam with our interactive quiz. Practice with comprehensive flashcards and multiple choice questions, each crafted to provide hints and thorough explanations. Master the exam with ease and boost your Scrum expertise!

When the Development Team cannot complete its work by the end of the Sprint, the framework of Scrum maintains that the Sprint length holds, and learning continues within that framework. This approach emphasizes the importance of adhering to the time-boxed nature of Sprints, which is a core principle of Scrum.

In this situation, the team should analyze what impeded their progress during the Sprint and use the Sprint Review and Sprint Retrospective to reflect on their performance, understand challenges, and improve their processes for future Sprints. The incomplete work is not discarded; instead, it may be addressed in the next Sprint if deemed valuable. This allows the team to learn from the experience, enhance their estimation and planning processes, and improve their overall workflow.

This focus on continuous improvement, rather than changing the Sprint duration or discarding work, is fundamental to Scrum's iterative nature. It helps teams develop a reliable cadence and fosters an environment where they can work collaboratively, reflecting on their performance while making adjustments as necessary for the future.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy