What is the responsibility of the Development Team regarding the Sprint Backlog?

Prepare for the Professional Scrum Product Owner I (PSPO I) Exam with our interactive quiz. Practice with comprehensive flashcards and multiple choice questions, each crafted to provide hints and thorough explanations. Master the exam with ease and boost your Scrum expertise!

The responsibility of the Development Team regarding the Sprint Backlog includes tracking the total work remaining throughout the Sprint. This task is crucial for monitoring progress toward the Sprint Goal. By keeping an accurate account of the work left, the Development Team can make informed decisions about how to manage their workload and adjust their efforts as needed. It helps them identify any potential risks to achieving the goal and allows for transparency, not just within the team, but also with stakeholders.

Tracking the total work remaining also enables the team to assess their pace and productivity during the Sprint. This information is often visualized in charts or burn-down graphs, fostering a shared understanding of progress among team members.

The other responsibilities mentioned in the options pertain to different roles or are not accurate representations of the Development Team's duties concerning the Sprint Backlog. For example, creating initial backlog items typically involves the Product Owner, while delegating tasks is not within the Scrum framework for Development Teams, as they are self-organizing. Communication with stakeholders is generally the responsibility of the Scrum Master and the Product Owner, rather than the Development Team itself, though they may engage with stakeholders as needed.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy