During which event does the Development Team demonstrate their work to stakeholders?

Prepare for the Professional Scrum Product Owner I (PSPO I) Exam with our interactive quiz. Practice with comprehensive flashcards and multiple choice questions, each crafted to provide hints and thorough explanations. Master the exam with ease and boost your Scrum expertise!

The Sprint Review is the specific event where the Development Team showcases the work they have completed during the Sprint to stakeholders. This event is designed to gather feedback and foster collaboration between the Development Team and stakeholders. During the Sprint Review, the team demonstrates the Product Increment, which represents the sum of all the work completed in the Sprint, and discusses what was accomplished as well as what was not. This feedback loop is crucial for adapting the product to better meet user needs and for planning future Sprints based on stakeholder input.

In contrast, Sprint Planning is focused on what will be worked on in the upcoming Sprint, making it an event centered around planning rather than demonstration. The Sprint Retrospective is dedicated to reflecting on the past Sprint and identifying areas for improvement within the team's processes, not a showcase of work. The Daily Stand-Up is a quick daily meeting for the team to synchronize activities and address immediate challenges, but it does not include formal demonstrations to stakeholders.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy